Dongfang Electric Group ultra supercritical thermal power project host contract signing
on June 8, Dongfang Electric Group and Heqi power plant briefly introduced the special experimental machine for testing steel strand in Jinan. 2 × The signing ceremony of the main engine contract of 660 MW ultra supercritical thermal power project was held in Zhengzhou
on June 8, Dongfang Electric Group and Heqi power plant agreed on 2 × 660 inaccurate positioning megawatt ultra supercritical thermal power project host contract signing ceremony was held in Zhengzhou, 1045 loss making enterprises
fanxiufang, mayor of Zhengzhou, zhulianchang, general manager of Henan Investment Group Co., Ltd., and zhangzhiying, executive vice president of Dongfang Electric Co., Ltd. delivered speeches at the ceremony. Liu Xinyong, member of the Standing Committee of the municipal Party committee and vice mayor, and Duan an and Li Xingjia, deputy general managers of Henan Investment Group Co., Ltd., attended the signing ceremony
this contract mainly involves the three main engine equipment of Heqi power plant: boiler equipment, steam turbine equipment and generator equipment
Zhang Zhiying said in his speech that Dongfang Electric Group would earnestly perform the contract, pay close attention to the early technical preparation and production preparation, and repay the trust and support of Henan Investment Group Co., Ltd. with excellent product quality and timely delivery. At the same time, we also firmly believe that with the strong support of Hebi municipal Party committee and government, Dongfang Electric Group will sincerely cooperate with Henan Investment Group Co., Ltd., support each other, implement various preparations, ensure the smooth operation of the project, and make due contributions to the economic and social development of Hebi city with an accuracy of 0.1mm